The first part of this page is
about the work I did when I first got my house.Further down the page there is
more about subsequent projects including my new porch and my side and rear
extension.
Renovation
I originally put this page together to show the house that I bought and
re-wired, re-plumbed, re-built, re-furbished, renewed. Basically I changed a
lot, walls and ceilings came down and went up, floors came up and went down, the
chimneys were removed (makes a huge difference to the size of the rooms without
the chimney brests, particularly the bedrooms), the stairs were stripped down,
the garden was re-planted, the useless garage rebuilt as a decent shed, with a
nice sized deck and pergola next to it and the driveway was dug up and a new
one put in. The only things I did not do personally, to some greater or
lesser extent, were the gas, the new warm-air heating system, the carpeting and
the driveway. Everything else I had a hand in although I had some people
helping, mostly for labour. Those who did that much more were: My dad who did
much of the electrics (he is an electrical engineer, amongst other things
anyway); my mum helped with some of the plants for the garden; my friend David
helped out with some of the lighting; David and Jocelyn, my neighbours to one
side, painted my fences (their idea not mine, although much appreciated);
David's uncle John did some of the plumbing; a plasterer did most of the
plastering and a structural engineer was involved in the structural supporting
of the remaining chimney stack (there is a lot of weight there, previously
supported by the chimney brests).
All my neighbours were very supportive, often
helpful, generally inquisitive and never complained about the noise and
disruption to their lives.
The work was all done in three months which is quick by anyone's
standards and was all-consuming of my time and energies during the process. As a
result there are not as many pictures as I would have liked, nor are many of
them of fantastic quality as I was preoccupied with other things.
Some odd bits of trivia if you care, is that I estimate that
around eighty tonnes of waste was removed during the three month period and
there was over a mile of new cabling put into the place.I have decided to organise the pictures by room, as I
think it most clearly shows the changes that took place.
_______________________________
These pictures show the front of the house, apart from the
guttering, some painting where necessary and cleaning, the driveway was the most
major change. The last photo was actually taken a year later. The previous driveway was paved with
inadequate paving slabs without any foundation, the new one is a nice block
built one with a small garden area.
Downstairs
The entrance hall of a home gives a first opinion and feeling
for a place, the hallway when I bought the house was dark, dirty and dismal. I
lightened it not only by painting the walls white (the whole house is painted
white actually, I like the minimalist thing, which also makes the place feel
more spacious), but also by cutting the panels out from the banister going up
the stairs. The under-stairs cupboard doors were also replaced with wooden ones.
The absence of the radiator (replaced with a small vent in the floor for the
warm-air system) also gives a feeling of more space. The carpet on the stairs is
lighter and the floor is a light coloured wood. I also stripped the banister
down to the bare wood and treated it, giving a warmth to the area that might
otherwise be too sterile. The wooden floor and lamp shade also give a bit more
warmth.
The front reception room had peeling, dirty paper, a disgusting
carpet, poor lighting and a blocked fireplace that had several dead crows in.
The chimney brest was removed the ceiling re-plastered and fitted with dimmable
recessed spot lights. The wall where the chimney had previously been also needed
plastering. The flooring was replaced with the same wooden flooring as
throughout the downstairs.
The rear reception room previously was poorly lit, papered with
a horrible chintz and had Artex on the ceiling (I strongly believe Artex should
be banned outright). The chimney brest was removed here too, the ceiling
boarded, plastered and fitted with dimmable recessed spot lights. The wall where
the chimney had previously been also needed plastering. The flooring was
replaced with the same wooden flooring as throughout the downstairs.
The Kitchen previously was poorly lit, dirty, unventilated and
the space was inefficiently used. The tiles were actually laid on top of another
layer which in turn had been cemented in place. These were removed (a lot of
chiseling involved) as was the dangerous wiring and antiquated pipe-work. The
floor was solid in some areas (probably for an oil or coal burner when the house
was built). That was removed and new beams and hangers put in place as
under-floor space was needed for the hot-air ducting and as also I wanted the
gas pipe to be under the floor as opposed to through the wall as it had
previously been. An extractor chimney and fan was installed over the five ring
gas hob. Three separate ring mains were installed, one for the cooker, another
for the sockets powering the washing machine, refrigerator and other similar
appliances, the last ring is for the sockets at worktop height. The reason for
doing it this way was that if for example someone put a metal object in the
toaster it would break the circuit causing them and the toaster as little damage
as possible, but would not stop the wash cycle on the washing machine or turn
the fridge / freezer off at the same time. The cooker is always on a separate
ring. The gas boiler and cooker were removed, replaced by a boiler in
the loft, the warm air heater is also in the loft and the new cooker is
electric. The ceiling was fitted with recessed spot lights highlighting each of
the work areas and the basin. The flooring was replaced with the same wooden
flooring as throughout the downstairs. The refrigerator is actually in what was
originally the coal store and later a larder. The aperture was increased and now
accommodates a proper size fridge/freezer. The cupboards have a beech finish to
compliment the floor and the cooker, chimney, splash-back and electrical
fittings are all in in brushed stainless steel to match the sockets and switches
throughout the house. There is now much more cupboard space but the room is more
spacious. In the future I extend the kitchen as I like to
cook and prefer more space. However, this is more than adequate in the
meantime.
The downstairs toilet was previously dank and dark, the toilet
itself was reminiscent of those found in schools and hospitals and there was no
hot water plumbed to the sink. The wooden floor that runs throughout the whole
downstairs is also found here, the radiator went (replaced by another hot-air
vent), the back was paneled to give a cleaner look as opposed to the cable
boxing that previously existed. Furthermore, hot water was plumbed to the corner
sink.
Upstairs
The banister on the upstairs landing was taken down to the bare
wood and treated, the same as the one on the stairs. The light was changed and
the loft access was made into a hinged drop down trapdoor, with a pull down loft
ladder.
The front bedroom is actually the largest room in the house.
When I got the place there were fitted wardrobes that were not deep enough to
hang things straight in, the lighting was also poor and the decor atrocious. The
wardrobes and chimney brest were removed, the ceiling and walls re-plastered and
the floor extended to cover the cavity where the chimney previously was. A light
Berber carpet was laid and the lighting was changed to several low voltage
spots.
The back bedroom had similar problems to the front one. There
were fitted wardrobes that were not deep enough to hang things straight in, the
lighting was also poor and the decor atrocious. The wardrobes and chimney brest
were removed, the ceiling and walls re-plastered and the floor extended to cover
the cavity where the chimney previously was. A light Berber carpet was laid and
the lighting was changed to several low voltage spots. In addition though, there
was an airing cupboard access which was incongruous. This was removed and a new
wall put in place. This gave a cleaner look to the room and also provided a lot
more space and also more space in the bathroom.
The small bedroom, which is likely to be used as a study in the
future, was abysmally decorated. When stripping off the paper and paint though I
actually found that some of the previous colour schemes had been even worse. In
this room there was an old airbrick that had been stuffed with paper, it was
plastered over. Also as it is potentially going to be used as a study there are
proportionately many more power sockets than the other bedrooms. As per the rest
of the upstairs a Berber carpet was laid and the walls painted white.
The bathroom was completely rebuilt as previously it was very
small, with the airing cupboard taking an inordinate amount of space. That was
removed as was all the bad wiring (some old lead covered cables were still
there) and the old plumbing. The element heater was dangerous and one of the
first things to be taken out. The tiles in here were also two layers thick and
the bottom ones set in cement (the same as in the kitchen). They were removed
and the walls stripped down. A new bathroom suite was installed, with a large
vanity unit, full sized bath and a toilet (something there had previously not
been space for). The floor was tiled with large marbled, non-slip, grey tiles
and the walls in large white tiles with a black and grey band around the room to
stop it seeming too sterile. A glass shower screen was also fitted and recessed
directional spotlights improve the lighting.
The upstairs lavatory was a nasty, claustrophobic cubby hole
with a horrible plastic toilet. The linoleum floor was removed and the floor was
tiled with the same tiles as in the bathroom. The soil stack needed replacing as
an extension needed to be made to the new toilet in the bathroom next door. The
toilet was replaced and the lighting improved. Later this toilet disappeared to make a passageway to the future extension. It was with this in mind that I did not knock this through to make a larger bathroom in the first place.
The loft was dirty and had a lot of rubbish in it. It was
cleared out, properly insulated and boarded. It also now houses the hot water
boiler, warm-air heater and television aerial. The future is to have
a loft conversion as it is of ample size, although this was when the extension happened.
The line of sight in the garden was overly interrupted by the
pre-fabricated garage, which was of no practical use as a garage. I decided to
rebuild it at the back of the property, giving better security, noise
insulation, a visual barrier to anyone trying to look in from over the fence and
also to provide a good sized solid shed and workshop. The concrete base it was
laid on is between one and two feet deep (30cm to 60cm) and has been entirely
over-engineered. There is a mesh in it and the mix of cement to ballast is
equivalent to that used in a multi-storey car-park. It has power and lighting,
via an armoured cable running to the house. Next to the shed I made a large
soak-away which was filled with many of the bricks from the demolished chimney
brests and laid over with the crushed asphalt from the patio area. On top of
this I built a large deck and arboretum that I hope to train some climbing
plants and flowers over to create a tabernacle of sorts. A path was laid using some of the former driveway paving slabs
overlaid on a bed of sand. The border was extended down both sides and a number
of new trees and plants were planted. The lawn was also levelled a bit and the
grass rejuvenated.
Other things that I did during all this housework was put in
many more power sockets (one can never have enough in my opinion), there is
co-axial cable running all through the house from a distribution box in the
loft, that carries satellite, terrestrial and radio signals. There is also RJ75
multi-core cable running all through the house. This can be used for networking
or multi-room audio visual systems. I don't have one at the moment, but who
knows what happens in the future. The telephone system has also been expanded to
provide a socket in each bedroom and reception room.
Porch
After a few years living contentedly in my home, I decided it
was time to extend it. Starting with a porch. This was a test of my bricklaying
skills, as I had done an intensive course and so needed to put the newly
acquired knowledge to good use. I did everything in it myself, from the
foundations to the roof, including installing the doors etc. The only thing I
didn't do was the plastering and my ever reliable father was on hand to help out
with the wiring and some other bits and bobs. It was more work than it would
appear as I was doing it evenings and weekends after work etc. The weather was
also working against me. My pointing is quite deep, so the shadows from the
lights at night make the brickwork seem wonkier than is the case in reality. All
in all I've been pleased with my first construction.
Extension
The kitchen in my house has always been woefully small in my
opinion, so I have always had the plan to extend it. Whilst doing that it made
sense to add a garage / utility room. If you're doing one level, you might as
well do two. As the greatest costs are for the footings and the roof. So, I have
a two storey side and rear extension.
It all started, as these things have to at the bottom. The
foundations required a lot of digging, to which end I hired a mini-excavator,
which was quite good fun to use for a little while, until it got repetitive. The
clay in London is famous and around my way, it seems to be heavier, stickier,
wetter and generally more difficult to dig than it should be in a civilised
country. Thankfully the excavator did the majority of the dirty work. I had
previously covered my driveway with plywood to protect it. It also meant that
then we could pile all the muck there for a grab truck to take away there were
three full loads, the last ten or fifteen tonnes of the muck was disposed of
differently.
I was not able to dig the trench for my footing up to the site
boundary, as I feared that my neighbour's garage didn't have much foundation.
For this reason, my structural engineer specified a cantilevered foundation,
where a deep trench is next to where the walls are bearing down. When excavating
the footings, my worst fears were confirmed (better than being surprised) and it
was apparent that the garage in question had no foundation to speak of. If I
hadn't pre-empted this, it is extremely probable that in digging a trench nearer
the boundary, their garage would have slipped and collapsed. Thankfully, there
is now my foundation also pinning their garage in place. It has been a constant
source of amazement that their garage which is so abysmally built (no
foundation, horrendous brickwork, poor pointing) continues to stand as it has
for more than 45 years. The foundations
are 1200mm deep, largely to avoid any kind of frost, as well as protection
against tree root subsidence etc. In total about 120 tonnes of muck was taken
out of the ground, only to be replaced by a load of concrete and steel
reinforcing mesh (A252- 8mm).
A couple of days after the concrete had been poured (I got
Ready-Mix pumped in as it would have been a nightmare to do it any other way),
we were able to get the first bricks down. In a day, the majority of the site
was up to DPC (damp-proof level). Once that was the case, it was then possible
to put in the cavity insulation and just get the bricks and blocks up to
ground-floor ceiling height.
When that had been reached, some of the outside wall had to be
removed from the kitchen, in order to insert the larger 4800mm steel (USJ 203mm
46kg/m c/w 250x6mm plate) of the T to be installed. We manhandled it into place,
despite it weighing about half a tonne. A padstone was then made in situ at
either end. Once some plumbing issues had been resolved, the padstone at the
existing wall end was extended. On the far end, the beam was placed on a pier of
engineers bricks. On top of that steel, it was then possible to build up to
ceiling height on the first floor. Inserting spaces for windows and lintels as
required. Later, the second steel to make up the T (USJ 150mm c/w 250x6mm plate)
was inserted and bolted using the cleat and M20 bolts.
Floor joists for the first floor were put in and the roof
of the rear single storey extension was waterproofed, battened and tiled.
In the garage / utility area, the soil pipe had to be rerouted
from upstairs, the soil stack for the extension also had to be brought in. The
drainage for the utility room also needed to be plumbed, as well as the water
supply brought in before the concrete floor was poured. This was done on top of
some insulation to keep the floor warmer, a DPC to keep the damp out and some
more A252 steel mesh to keep the thing as hard as nails. A box was made for the
manhole in the middle of the floor, where a second manway is installed above.
This was reached in three and a half weeks from starting excavating the
footings.
Whilst waiting on getting the roof done, I laid the majority of
a new patio and dug a big soakaway, in order to cope with the added water I'd be
getting on my bigger roof. As the soakaway had to be some distance from the
building, it also meant digging a long trench to take the pipe which would take
the water away. Once it was all done, a concrete cap was put on the soakaway and
some weeks later the lawn was returfed.
Once I got some people to do the roof work, I got the scaffold
put up, which gave not only good access, but also nice views of the area and my
neighbours.
The first thing the roof people did was take away my existing
chimneys, whilst wearing rubbish bags. That should have been a portent of things
to come, however we soldiered on through the worst August rainfall since Noah
went for a sail. At times this meant that as their waterproofing was far from
adequate, it would rain inside as well as out. Not ideal to be woken up by rain
when you're in bed, especially when the rain is in the bedroom.
As the roof was being built, I got to work preparing the first
floor. we knocked out the existing single toilet, which made the landing bigger
and created an access to the extension upstairs. After knocking it out, I had to
rebuild some walls in block and other new walls to divide the new bedroom and
bathroom. As I was doing this Wieshek who had been doing some electrical work
for me turned up wearing a plastic bag for a hat - I'm still not sure why.
The roof was insulated with some very effective solid
insulation, which was later put under the kitchen floor too. It was very
satisfying to finally see the shape of the new roof come together, despite the
various false starts, when the guys building it got the measurements so wrong,
it would have been completely pointless.
Once they were done, the roofers were able to come along to
felt, baton and tile the thing as well as making the dormer waterproof and
making a very nice valley gutter.
It was nice to be able to get the upstairs plastered and
painted. The landing also needed levelling as there was a step down from the
steel beam. With some sheets of plywood taken off the driveway, the whole thing
got a lot more level.
A big impetus for having all the work done was to replace what
had been a very small kitchen with a much larger one. It actually became four
times the size of the original, with an adjoining utility room / garage and
conservatory.
The Finished Rooms
The Kitchen units were supplied by the very helpful folk at Casa
Cucina in Cockfosters, tell them I sent you and I'm sure they'll be nice to you
too. The electrical appliances and sink were mainly acquired from an internet
shop. The hob, splashback and extractor were from the previous kitchen. The
kitchen was assembled by me. The worktops are Maron Cohiba granite and the floor
is tiled in Giallo Imperial granite, supplied by good friends at UK Stone Ltd.
They installed the worktops and their precision in getting the sink positioned
was accurate to a tolerance of one millimetre, an impressive job indeed. There
are two single ovens next to each other, this is for several reasons. I think it
is a good aesthetic, it also gives much more cooking space than a double oven
and is more efficient. They are also side opening ovens (difficult to get hold
of) which makes it safer for those of lesser stature to get things in and out of
the oven. The dishwasher is a two drawer Fisher & Paykel (next to the sink). The
microwave is a standard one, which is actually inside one of the lower units, as
I don't particularly like most of the integrated microwaves and they are also
extremely expensive with less internal volume. I also don't much like the
integrated coffee machines, which is why I have a free standing one. The waste
(three bins: organic, recycling and general waste) are all under the sink. All
the doors and drawers have Blum soft close mechanisms (pistons for the doors,
blumotion for the drawers).
The conservatory was supplied and erected by Everest. I
preferred their design and also wanted to go with an established brand as the
life expectancy of most conservatory companies is less than for a motorcycle
courier. All the windows open fully, with egress hinges, which means that they
go perpendicular to the building line. I built the base and walls, they simply
supplied the conservatory. The French doors threshold is at a level so that
there is no step when stepping out, something the designers found peculiar but
accepted the merits of. I may for the first time concede that I put too many
power sockets in the conservatory, as there are seven doubles. This doesn't have
any negative effect and was a minimal extra expense and effort. The lights were
sourced to throw the light across the room without creating a glare. It it
surprisingly difficult to find wall mounted lights that do this. The wall
mounted air-con is also a heater that was particularly cheap at my local
wholesaler. The glass is argon filled, double glazed, energy efficient,
self-cleaning glass. The floor is tiled with the same Giallo Imperial granite as
in the kitchen. The fire pit in the third photo has a removable centre-piece and
is also Maron Cohiba granite to match the kitchen worktops. This was also
supplied by my friends at UK Stone Ltd.
I built the pond with excess bricks, it has a waterproof render
inside. The Tiling on the wall is the same as the patio, Indian Sandstone. The
stone on the wall has a different sealant on it, which gives it a slightly
different appearance. The pond has different types of carp in it (koi and
butterfly). The water is pumped to a filter behind the wall (which is also a
storage area and where all the electrics are). From the filter it goes up two
metres to the water feature which is a form of weir that creates a sheet of
water falling down to the pond, helping to aerate it and looking very nice. This
was made from a sheet of aluminium my father had in his shed for many years, it
was shaped, riveted, sealed and had hose attachments fixed to it before it was
mounted. There are timed lights in it to illuminate the pond and water feature
at night and prevent it freezing in winter.
The utility room adjoins the kitchen. The majority of the units
were from the previous kitchen. A few additions were made and acquired during a
sale. The door and drawer fronts were all replaced with genuine solid maple in a
shaker style. With the additional space, a larder freezer and tumble dryer were
added. The washing machine was from the previous kitchen. A Kinetico water
softener was added. To comply with fire codes there is a fire door with a
self-closer, between the kitchen and utility room. It also makes it more secure.
The front of the utility room is a shuttered, secure, roller door. This gives
easier access for bulky items as well as making it possible to take the wheelie
bins all the way through to the garden when necessary. The floor is tiled the
same as the kitchen and conservatory. There is a modest step to comply with
regulations.
The window in the downstairs toilet was bricked up, as it was
facing into what became the utility room. This was replaced with mirrors on two
sides, which helps create a sense of more space in quite a cosy room.
A landing was created at the top of the stairs. A balustrade was
put in place to comply with building regulations. Unfortunately, it wasn't
possible to find a similar balustrade to the existing one. What was previously a
window was turned into a niche for some of my art and artefacts.
The landing leads around to the new bathroom and an additional
bedroom. As I already have one spare bedroom, this is currently the Massage
Room. Where my friendly masseuse sorts out my back when it gets troublesome.
The bathroom is tiled with natural limestone. Supplied once
again by my friends at UK Stone. The floor has the same stone but with a
'leather' finish, to minimise slipping if it is wet. There is a teardrop bath to
maximise the space in it, particularly when showering. It also doesn't have any
taps in it but fills from the overflow. The shower has jets as well as a large
rose, so that even the filthiest person can be cleaned with minimal effort. It
was decided that a wall cabinet wouldn't have looked right in this bathroom, so
a simple square mirror is placed above the vanity unit.
From the back garden, one can see the extent of the extension.
This included creating a patio and repaving the path all the way up to the shed.
The house has effectively doubled in size with the additional space in the loft
created by the dormer. I forgot to change the colour of the bricks at the rear
of the building, as they are different to the front. This makes it easier to see
the extension at the rear than the front, where the brick style more closely
matches.
Now what would be nice, is some decent weather when I can enjoy
the fruits of my labour. |